Resource management

The Resource Management function provides schedulers with the ability to account for and report on the project resources such as labor, materials, or equipment that are needed to plan the scheduled work.

From a shared organization resource pool, schedulers can assign the required resources to activities. With the resource utilization data, cost and time impacts can be assessed in a time-phased manner.

Import resources from Knowledge Base Resource register into Project Resources Register

  1. Click the Import Resources icon, and then select Knowledge Base from the Import Type drop-down menu.

  1. Select the Knowledge Base resources that you want to include in your project, and then click Import. A caution symbol shows when the resource already exists and that it will be duplicated.

  2. A message shows when the import is successful. Click OK.

    The selected resources are now imported into the project from the Knowledge Base Resource register.

Resource assignments

Resources are assigned to activities (activity level) but can also be set via work packages (summary level) in the schedule. You can assign the same resource multiple times to a single activity.

The setting that allows the same resource to be assigned more than once is On by default. If needed, with the applicable permissions the toggle can be set to Off in Schedule Configuration > General > Enable Duplicate Resource Assignments.

If you are using the integration with Estimate, you can import activity resources so that cost item resources defined in Estimate are brought directly into Schedule activities. Each cost item converted into a schedule activity includes its associated labor, equipment, and material resources, along with their units and types. For more information, see Integrated Solutions InEight Integration Estimate-Schedule. The imported resources data is read-only, so any resource changes must be made in Estimate and then synced to Schedule.

Assign resources at the activity level

  1. In Plan view, you can access the resource assignments of the assigned by using either of the following options:

    • Open an activity’s details in Iris, expand the Resource Assignments section, and then click Modify.

    • Customize the Gantt Chart view to include the Resources Column, and then select the Resources icon in the Gantt Chart.

    • Show Resource Assignments column in Plan view

  2. A dialog opens that shows the resource assignments for the activity. In the Available Resources section, select the resource.

    All available resources can be found quickly using the Search function in the resource assignment dialog box. If a resource cannot be found or a project-specific resource needs to be added, see Add project resource in Resource assignment.

  3. After the resource is selected, click the arrow icon to add the resource to the activity’s Resource register. You can also double-click a resource to add it to the Resource register.

  4. When the resource is added, details for each resource can be modified for the activity. Fields that can be adjusted at this level include Curve, Units/d, Cost/Unit, FTE/Qty, and Plan.

Resource driven durations

When there is more than one resource for an activity in Plan view, you can select a resource to dictate the start, finish, and overall duration of an activity. The other resources in the activity are calculated based on the duration of the driving resource.

By default, the system selects the resource with the largest unit quantity, but you can manually choose a different resource.

Add driving resource for an activity

  1. In Plan view, select an activity from the list that has resources, and then click Smart Planning in the Iris panel.

  2. In the Remaining (d) field, click the R icon to open the Set Productivity Rate dialog box.

  3. On the Resources tab, it shows a list of the resources assigned to the activity. Click the radio button to select the resource that you want to use as the driving resource.

  4. Click Apply Rate. The Set Productivity Rate dialog box closes.

    You can change the driving resource by selecting another resource and clicking Apply Rate.

  5. Click Resource Assignments in the Iris panel to expand the section and show the resources. Click Modify.

  6. In the activity resources, the icon in the resource ID field indicates the driving resource. You can make changes to the driving resource’s unit rate or remaining units, and it dynamically recalculates the activity duration and related Smart Planning fields.

Fill down

The Fill Down function lets you fill down a calendar, code or resource from the summary level. You select the items to fill down, the system fills down the selections and processes the items to all child level elements.

Fill down from the summary level

  1. Identify the summary level planning package to assign resources to, and select the Actions icon.
  2. In the Actions menu, select Fill Down.

    The Fill down window shows.

  3. On the Calendar tab, select from available calendars.

  4. On the Codes tab, select any Activity Code.
  5. On the Resources tab, select any Resource value.

  • All assignments made from this window flow down to all subordinate activities.

All available resources can be found quickly using the Search function in the resource assignment dialog box. If a resource cannot be found or a project-specific resource needs to be added, see Add project resource in Resource assignment.

Resources can still be edited further at the activity level even when set up from the summary level. Plan values cannot be edited when applying a resource at the summary level but can be adjusted at the activity level.

Resource histogram

After a schedule has been loaded with resources, Schedule can generate a resource histogram.

Generate a resource histogram

  1. In the Schedule’s Planning View, select the View options icon in the toolbar. The View options menu opens and shows the Histogram toggle.
  2. Set the toggle to On, which will show the resource histogram in the Plan view.
  3. A histogram shows below the Gantt Chart. The resource histogram plots resource utilization over time depending on the following:

    • Resource Settings Configuration Options: When the resource histogram is switched on, more settings become available for configuration.
    • Setting

      Function

      Resource Histogram

      You can switch the Resource Histogram view on or off.

      Comparison Mode Compares Current, Active Baseline, and Snapshots in the Resource Histogram.

      Status

      Filters histogram to show Planned, Actual resource quantities, Remaining or Remaining Late.

      Display

      Adjusts the Y-axis of the histogram to show Units, FTE, or Cost.

      Unit

      The resource’s unit of measure.

      S-Curve

      Switches on or off the S-Curve on the resource histogram.

    • Activity or summary level selected in the Gantt Chart: The resource histogram plots out data based on the activity or planning package selected in the schedule.

      The zoom level for the Gantt chart controls both the schedule and resource histogram X-axis units of time that is days, weeks, months, quarters, years or decades.

  4. Set the Resource Setting Configuration Status to Planned & Remaining. This populates the Resource Histogram with all planned and remaining resources for the activity or planning package selected.

  5. Change the Resource Setting Configuration Display from Units to Cost.

    • FTE stands for Full Time Equivalent, and is the count of people per time period.

    • Burn rate is the percent planned per period of time.

    • The Y-axis values are adjusted from resource quantities to dollars.

  6. Set the S-Curve toggle to On. This overlays the S-Curve on the resource histogram.

S-Curves reflect cumulative data. As the values increase over time, this reflects the accumulation of resource units/FTE/cost, depending on settings, over time.

Filtering by resource

Filtering by resource only applies if the stacked resource histogram is turned to On.In the filter functionality, the Gantt chart & resource histogram can be filtered to see planning packages and activities assigned specific resources. When the resource histogram is switched on, it can be used as an interactive filter as well. Selecting a Resource Name listed in the histogram or any of the resource bars will filter down the Gantt Chart and Resource Histogram to show only data pertaining to the information selected.

In the image below, the Resource Histogram is filtering based on the selected resource: Concrete Finisher.

Additionally, to modify or disable the resource filtering, users may click the filter icon to make adjustments to the filter parameters.

Histogram comparison mode

In View Options, you can view the histogram in comparison mode, when enabled.

When the Comparison mode toggle is set to On, the baselines and snapshots that exist in the Baseline/Snapshot Management show as a graph with the current baseline. The histogram compares resources rolled up to the category type and shows you resources as they trend.

Each line in the graph represents a baseline, snapshot, and the current estimate.

The histogram graph can now also be shown in units and burn rate.

You can also view the histogram with an S-Curve that shows you a cumulative trend line for each baseline, snapshot and current.

Export assignments

Schedule export functionality includes the ability to export resource assignments. You can export resource spread data that shows every resource and hours worked for every day of the entire schedule selected.

  • In Plan view, select the Export icon, then select the Resource Spread export type from the drop-down menu to send the data to a reporting API.

  • To export the data from the Project List page, select a schedule and then click the Generate resource spread export icon.

Project specific resources configuration setup

Resources in a project are either global resources or project specific resources. Global resources automatically populate a project’s resource register from the Knowledge Base. If a resource is not available from the established global resources, project specific resources can be set up.

Project specific resources are useful when the resource utilized is unique to that project and not applicable across the organization.

Establish project specific resources

  1. Select Schedule Configuration from the project drop-down menu.

  2. Select the Resources tab in the Knowledge Base.

This brings you to the project-level resource register

The Project level resource register functions the same as the Knowledge Base. See Setting up Resources for information about how to add resources and use the Import/Export functionality in the Resources register

Schedule possesses the concept of global and project specific resources. When you create a schedule, it does not populate the resources in the Schedule Configuration window, but you can import resources from the Knowledge Base to use in your schedule. Project specific resources can also be added from the resource assignment window in the planning view. See the Resource Assignment for more information.

Add project resource in Resource assignment

Project specific resources can also be created from Resource assignment in the Plan view.

Create a project resource via Resource assignment

  1. Without any resources selected, click the Add new resource icon.

    • The Add Resource opens to add a project specific resource.

  2. Enter the project resource information, and then click Add.